ARRANGEMENT OF TWO CROSSROADS OF THE PROVINCIAL ROAD 4 "PEDEGUARDA" RESPECTIVELY IN CORRESPONDENCE WITH THE OLD SEDIMENT OF THE PROVINCIAL ROAD 4 AND WITH THE PROVINCIAL ROAD 36 "DEL COMBAI" THROUGH THE REALIZATION OF TWO ROUNDABOUTS, Province of Treviso - VENETO
The project involves the arrangement of two crossroads in the municipality of Follina. The arranjement by roundabout of the first crossroad, localized in the south of the historic centre of Follina in correspondence of the graft between the old sediment of provincial road 4 and the current sediment i provincial road 4, includes a pedestrian-cycle path, a viaduct and a new lighting system. The second crossroad is localized in the north of the historic centre of Follina at the junction of provincial road 36 "del combai" with the current sediment of provincial road 4. The planned solution involves the construction of an elongated roundabout with revision of the intersection angles of the provincial roads.
Client
Municipality of Treviso
Date
2002 - 2005
Amount
€ 355 000 south roundabout
€ 600 000 north roundabout
Status of the work
shred 1 (south roundabout) - completed and tested works
shred 2 (north roundabout) - final design approved